iAutomate
947-201-6584
EN · i18n
LIVE
--:--:-- UTC
/PRJ-STL-047CASE STUDY · ENGINE ASSEMBLY

47-station engine line —
PPAP on time, zero escapes.

Master controls integration for a Stellantis Tier-1 engine assembly line in Michigan. Six OEM scopes unified into a single Allen-Bradley ControlLogix architecture with GuardLogix safety, Power & Free + floor loop coordination — launched on the contractual PPAP date with 99.2% first-pass yield and zero quality escapes.

/DATASHEETREF. PRJ-STL-047-001
CLIENTTier-1 Supplier · Stellantis
SITEMichigan, USA · adjacent to live prod
SCOPEMaster PLC · safety · launch + ramp
PROCESSEngine assembly · 47-station line
PLATFORMAB ControlLogix · GuardLogix · EtherNet/IP
DURATION16 weeks · kickoff to signed PPAP
47
stations integrated
99
.2% first-pass yield
0
quality escapes
16
weeks to PPAP
/01PROBLEM STATEMENT

Five constraints, one fixed date.

A contractual PPAP date, six OEM scopes, a live adjacent plant and a zero-escape quality bar — the controls scope had to consolidate all of it under one signed package.

/CH-01

Fixed PPAP date

The PPAP date with Stellantis was contractual and immovable. Any slip meant penalties and potential loss of the program.

/CH-02

Six OEM scopes to unify

Equipment shipped from six OEMs with their own PLC code, I/O standards and protocols. Someone had to own the integration.

/CH-03

Zero-escape quality bar

Engine assembly is safety-critical. Every torque spec, fastener sequence and interlock had to be validated — no escapes allowed.

/CH-04

Live-plant integration

Adjacent lines were producing. Cabling, commissioning and cutover had to happen without disturbing existing volume.

/CH-05

Power & Free coordination

Overhead Power & Free + floor loop conveyor required tight carrier tracking, accumulation and recovery sequences.

/02REFERENCE LINE

47-station engine line - top-view layout.

Schematic of the assembly line: overhead Power & Free carrier loop, the four assembly cells (short / long block, head, EOL test) on the floor loop, GuardLogix safety zones and the EtherNet/IP backbone to the master ControlLogix.

SCHEMATIC · LINE LAYOUT · REF DWG-STL-047
/PLANT · ADJACENT-LINE PRODUCTION ACTIVE · ZERO-DISTURB CUTOVER/POWER & FREE · OVERHEAD CARRIER LOOPCARRIER FLOW →C1C2C3C4C5/FLOOR LOOP · 47 ASSEMBLY STATIONS · 12 TEST/C1 · SHORT BLOCKST 01–14/C2 · LONG BLOCKST 15–26/C3 · HEAD + DRESSST 27–39/C4 · EOL TESTST 40–47SZ-1SZ-2SZ-3/ETHERNET-IP · BACKBONE · DEVICENET FIELD/PLC · CONTROLLOGIX L8 · MASTER/SAFETY · GUARDLOGIX · PLd/HMI · FT VIEW SE → MES
/P&FOverhead carrier loop · accumulation
/C1–C44 cells · 47 assembly stations
/SZ-1/3Safety zones · GuardLogix PLd
/L3ControlLogix master · MES upstream
/03ENGINEERING SOLUTION

Four work-streams, one signed package.

Master PLC, Power & Free, GuardLogix safety and on-site launch were owned end-to-end so the customer signed PPAP against a single integrator — not six.

/SOL-01WORK-STREAM 01

Master PLC programming

Single-author master logic on Allen-Bradley ControlLogix coordinating all 47 stations and the conveyor systems.

  • Station sequencing + interlock logic
  • Conveyor zone control + accumulation
  • Error handling + recovery routines
  • Production tracking + traceability hooks
/SOL-02WORK-STREAM 02

Power & Free integration

Overhead Power & Free coordinated with the floor loop and station handshakes.

  • Carrier tracking + routing logic
  • Accumulation zone management
  • Auto / manual mode transitions
  • Carrier-jam recovery sequences
/SOL-03WORK-STREAM 03

GuardLogix safety validation

Safety architecture built and signed under GuardLogix with documented function tests.

  • E-stop circuits + zone isolation
  • Light curtain integration
  • Two-hand control stations
  • Safety-rated conveyor stops · ISO 13849 PLd
/SOL-04WORK-STREAM 04

Launch + ramp support

Engineers on-site through SOP and the first 30 days of production.

  • Real-time troubleshooting during ramp
  • Operator + maintenance training
  • IPF mapping + documentation
  • 30-day post-launch warranty support
/04ENGINEERING DATASHEET

Line specification — as released.

The full datasheet as it left FAT and SAT under the Stellantis controls + safety standard. Every line was held through ramp and the first 90 days of production.

R6
REV · 06 · POST-PPAP
Signed under iAutomate QMS + Stellantis
/DATASHEETREF · DS-STL-047
PLCAllen-Bradley ControlLogix L8
SAFETYGuardLogix · ISO 13849 PLd
NETWORKEtherNet/IP backbone · DeviceNet field
HMIFactoryTalk View SE · PanelView Plus
CONVEYORPower & Free overhead + floor loop
STATIONS47 assembly · 12 test / validation
TORQUEDC tooling · per-fastener traceability
VISIONInline presence + orientation checks
TRACEABILITYCarrier ID + per-engine genealogy
DATAOPC UA → MES · production + quality
STDStellantis controls + safety standard
QMSiAutomate QMS · FAT + SAT signed
/05PROJECT LIFECYCLE

From kickoff to signed PPAP.

Five gates, sixteen weeks. Each gate produced a controlled deliverable signed under our QMS — including the safety function-test pack and FPY capability that cleared PPAP.

01T+0
/KICKOFF

OEM scope unification

DELIVERABLE
DOC-01 Master I/O + protocol map
02T+4W
/DESIGN

Master PLC architecture

DELIVERABLE
DOC-02 Logic spec + safety matrix
03T+9W
/INTEGRATE

Station + conveyor commissioning

DELIVERABLE
DOC-03 Station-by-station signoff
04T+13W
/QUALIFY

Safety + run-off

DELIVERABLE
DOC-04 Safety FT + FPY capability
05T+16W
/PPAP

PPAP + launch + 30-day support

DELIVERABLE
DOC-05 Signed PPAP + IPF package
/06FIELD REPORT

Launched, ramped, held.

The numbers below are from PPAP and the first 90 days of production — measured on the line, not on a buy-off cell.

  • PPAP delivered on the contractual date · week 16
  • First-pass yield 99.2 % within month one
  • Zero quality escapes across initial production
  • Unplanned downtime under 15 min / shift through 90 days
  • Six OEM scopes signed off as one master package
REQUEST PROJECT CONSULTATION
/RESULTS · BEFORE → AFTERDOC · CASE-STL-047
METRICBEFOREAFTER
Launch dateFixed PPAPOn time · wk 16
First-pass yield98 % target99.2 %
Quality escapesZero allowed0
Unplanned downtimeBaseline<15 min / shift
Stations integrated6 OEM scopes47 unified

"iAutomate consolidated six OEM scopes into one master architecture and held the PPAP date. The line ramped clean and stayed clean."

POWERTRAIN ENGINEERING · TIER-1 · STELLANTIS PROGRAM

/CTANEXT STEP

Need a line launched on
a fixed PPAP date?

Powertrain, BIW or assembly programs where the launch date is contractual and the OEM scopes are scattered. Talk to a master-PLC engineer this week.