
Master controls integration for a Stellantis Tier-1 engine assembly line in Michigan. Six OEM scopes unified into a single Allen-Bradley ControlLogix architecture with GuardLogix safety, Power & Free + floor loop coordination — launched on the contractual PPAP date with 99.2% first-pass yield and zero quality escapes.
A contractual PPAP date, six OEM scopes, a live adjacent plant and a zero-escape quality bar — the controls scope had to consolidate all of it under one signed package.
The PPAP date with Stellantis was contractual and immovable. Any slip meant penalties and potential loss of the program.
Equipment shipped from six OEMs with their own PLC code, I/O standards and protocols. Someone had to own the integration.
Engine assembly is safety-critical. Every torque spec, fastener sequence and interlock had to be validated — no escapes allowed.
Adjacent lines were producing. Cabling, commissioning and cutover had to happen without disturbing existing volume.
Overhead Power & Free + floor loop conveyor required tight carrier tracking, accumulation and recovery sequences.
Schematic of the assembly line: overhead Power & Free carrier loop, the four assembly cells (short / long block, head, EOL test) on the floor loop, GuardLogix safety zones and the EtherNet/IP backbone to the master ControlLogix.
Master PLC, Power & Free, GuardLogix safety and on-site launch were owned end-to-end so the customer signed PPAP against a single integrator — not six.
Single-author master logic on Allen-Bradley ControlLogix coordinating all 47 stations and the conveyor systems.
Overhead Power & Free coordinated with the floor loop and station handshakes.
Safety architecture built and signed under GuardLogix with documented function tests.
Engineers on-site through SOP and the first 30 days of production.
The full datasheet as it left FAT and SAT under the Stellantis controls + safety standard. Every line was held through ramp and the first 90 days of production.
Five gates, sixteen weeks. Each gate produced a controlled deliverable signed under our QMS — including the safety function-test pack and FPY capability that cleared PPAP.
The numbers below are from PPAP and the first 90 days of production — measured on the line, not on a buy-off cell.
"iAutomate consolidated six OEM scopes into one master architecture and held the PPAP date. The line ramped clean and stayed clean."
POWERTRAIN ENGINEERING · TIER-1 · STELLANTIS PROGRAM
Powertrain, BIW or assembly programs where the launch date is contractual and the OEM scopes are scattered. Talk to a master-PLC engineer this week.